Washington Primary Care Centre
Week 38 of 60. On programe for completion on 1st August 2008.
All brickwork and windows are now complete. Base coat of Sto render has been applied. Cladding approx 70% complete. Still awaiting arrival of fascias and parapet flashings.
1st fix plumbing and electrics progressing internally. Internal partitions approx 50% complete.