Posts by Rob Partlett

24 Jun 2011

Hub Two nears completion

Images taken recently at Hartlepool Innovation Centre – Hub Two.

Client: UK Steel Enterprise Limited
Project: Hartlepool Innovation Centre – Hub Two
Main Contractor: Mansell
Procurement Method: Design & Build
Build Cost: £3m
Completion Date: July 2011


External Images


Internal Images

11 May 2010

Blaydon Primary Care & Leisure Centre

Work is progressing well at Blaydon with completion targeted for September 2010 as per original programme.

P+HS Architects are responsible for the design of the Primary Care Centre, while S&P Architects are responsible for the Leisure Centre.

The project is being delivered under the scape procurement method.

Contractor: Willmott Dixon Limited

Contract Value: £17.5m approx [AMP]

Completion Date: September 2010

25 Jun 2009

Blaydon Primary Care & Leisure Centre

Work has started on the new Blaydon Primary Care / Leisure Centre.

P+HS Architects are responsible for the design of the Primary Care Centre, while S&P Architects are responsible for the Leisure Centre.
The Primary Care Centre concrete driven piles and pile caps are now complete and erection of the steel frame is underway [approx 20% complete], the Leisure Centre steel frame is due for erection on 24th August, Week 22.
These photographs were taken from the raised viewing platform between the Willmott Dixon site offices.

The project is being delivered under the scape procurement method.

Contractor: Willmott Dixon Limited

Contract Value: £17.5m approx [AMP]

Completion Date: September 2010

Week 6 of 78

Week 6 of 78

Week 8 of 78

Week 8 of 78

Week 13 of 78

Week 13 of 78