5 Feb 2010

P+HS have achieved design stage BREEAM Excellent (total 72.57%) for the new Linac building NUH with an extra 2.5% to spare. Well done team.
Posted by robertcleavin in Misc
• Post a comment
5 Nov 2009

The new NUH building making good progress.
Posted by robertcleavin in NUH LINACs
• Post a comment
3 Nov 2009

28th October 2009 photograph
Main entrance and stair 01 steelwork has been erected.
Posted by robertcleavin in NUH LINACs
• Post a comment