Posts by James Gordon

1 Mar 2010

NUH LINACs close to partial possession

ramp needs some work.

Staff Entrance : ramp needs some work.

Main Entrance Barrel

Main Entrance Barrel

South East Corner

South East Corner

The LINAC bunkers which form part of the new Radiology department for Nottingham University Hospitals is nearing it’s April deadline for it’s partial handover .  The Bunkers which form the main body of the building will be handed over to allow the 6 month commissioning period for the specialist machines to commence.

Work will continue on site to the exteranl envelope and the Mould workshops and fittings areas as programmed for the buildings completion later this year.

17 Sep 2009

NUH LINACs off to a flying start..

Following the successful opening ceremony attended by hospital trust chief executive Dr Peter Homa, on the 4th of September, The first delivery of steelwork is being erected on site. Due for completion in July 2010, the Bunkers themselves will be handed over in March to allow the fit out and commision of the Linear Accelerators.This new facility being developed with Medicinq Simons under the NHS ProCure 21 Framework, will allow the NUH Trust to achieve the reduction in Cancer waiting times set down by the National Radiotherapy Advisory Group (NRAG).
.
View North to South of New LINAC Facility

View North to South of New LINAC Facility

View 'inside' Atrium

View 'Inside' of the main Atrium

View of Bunkers under construction.

View of Bunkers under construction.

20 Mar 2009

BS8300:2009

  • The recommendations on steps, stairs and handrails reflect those in BS 5395-1.
  • There has been a relaxation of the recommendations on the provision of vision panels in doors, and more detailed information is given on the location and design of door opening and closing furniture.
  •  More information is now provided on means of escape and references are made to BS 9999.
  •  An increased percentage of accessible bedrooms is now recommended.
  •  New subclauses have been included on accessible baby changing facilities and Changing Places sanitary accommodation.
  •  Information on achieving sufficient visual contrast has been revised and included in a new annex that makes reference to BS 8493 on the measurement of light reflectance values.
  • A new annex on slip resistance has been included, drawing on guidance issued by BRE and CIRIA.

 

 

These however are not exhuastive and reference should be made to the document itself online through The Construction Information Service.

31 Oct 2008

Nuffield Healthcare Warwickshire Hospitals

Stage one recovery.

Photograph shows the recently refurbished Recovery area. The previously open recovery area has been enclosed inline with the requirements of HBN26.  Tormax glass sliding doors have been introduced, with split sandblasting, to provide privacy for patients and still maintain an visual link between Theatre staff.

31 Oct 2008

Nuffield Healthcare Warwickshire Hospital - Theatre Two.

Photograph shows Theatre two recently refurbished including new doors and nurse workstations.

31 Oct 2008

Nuffield Healthcare Warwickshire Hospitals

Stage One Recovery

Due for handover 3rd November, the photogrpah shows the internal view of the recently refurbished and enclosed Stage one recovery area.  All M&E including medical gases have been upgraded. We’ve introduced a central Nurse workstation. The flooring has been setout to mirror the curtain tracks, as previously seen at Nuffield Newcastle.  Also as Newcastle we have utilised Reglit glass screens, through out the Theatre department, to break up and provide interest into what would otherwise be large areas of blank walls.

29 Sep 2008

Royston Lifelong Learning Centre Opens it’s doors

Doors Open!

Royston lifelong learning centre opened it’s doors on 15th September 2008, following the fit out of the library. Some fit out works are still being carried out to the first floor learning areas, but the library and CIS are being well used by the local community. This is one of the last projects to be developed by Barnsley Metropolitan Borough council inconjunction with the European Objective 1 funding.

19 May 2008

Royston Lifelong Learning Centre

1main-rear-entrance.jpg

Week 40 of the programme, due for completion in June 2008. Scaffold down the photograph shows the rear of the building. This will be the main staff and out of hours entrance. The galvanised pipes running parallel up the gable end are the supply and air extract for the fuel to the biomass bolier. The pellets are pumped upto the hopper room on the first floor, and then gravity feed the boiler on the ground floor.
 

19 May 2008

2-main-entrance.jpg

Photograph shows the curtain wall bays, which will be the main pedestrian entrance to the Centre. There are some additional finishing works to be carried out to the externals, including a perimeter powder coated steel channel.

19 May 2008

2a-main-entrance.jpg

Photograph shows a sample of the palette of materials utilised at Royston, Sandtoft interlocking clay Cassius tiles, Weber  Pral H system through coloured render and Finforest thermowood.

19 May 2008

Royston Lifelong learning centre - Main corridor

3internal-corridor.jpg

Photograph shows the first floor main corridor. The natural light is being provided through the Xtralite triple skin barrel vault skylights.

19 May 2008

Royston Lifelong learning centre - Tree protection.

4tree-protection.jpg

Photograph shows the CellWeb Tree Root Protection System,  This was a requirement of the planning approval from the Arbicultural officer for protecting the trees roots during the excavations for the new drainage. It is permeable and can offer a permenant ‘no dig’ solution for new access roads, however in this case it is providing temporary protection for the duration of the works.

25 Mar 2008

Royston Lifelong Learning Centre

royston-gen2.jpg

Wk 31 of the programme, completion set for June 2008. This view of the rear gable shows the pre treated Thermowood battens and cladding from Finn Forest, being fixed inplace. It is expected the timber will fade slightly, but should not lose as much of its original colour as Cedar for instance. Areas of this cladding have been treated for spread of flame, due to the proximity of adjacent (mostly glazed) squash courts. We have resisted the urge to infill the panels with render for the mock Tudor look.

25 Mar 2008

Royston LLC - First Floor

royston-int.jpg

A view from the main staircase across the first floor. Eventually internal partitioning will obscure this view, but we can see the insulation inplace across the entire floor, prior to the Under floor heating pipes being laid.

25 Mar 2008

Royston LLC Site Visit

royston-l_l.jpg

Ryan Meadows and Joe Stenson, P+HS’s very own little and large, visit site.  This was Joe’s first site visit with P+HS, where as Ryan was dragged out to answer for some of his handy work.